Wednesday, February 22, 2017

The big cob-house update

The last time we showed you our cob house the roof frame was beginning to go up, back in October. I'm taking a step back to show the whole process of getting the roof up. By the end of this post the house will have developed dramatically. I hope you enjoy these photos.

October 17, 2016 - The house unprotected. For a year we had a tarp over the house to protect it from the rain. Guests slept in the rustic rooms with good windows and doors but only a large blue tarp to cover it.
Oct. 19 - The roof structure goes up.

The recycled tiles are made from used milk boxes - heating and molding the aluminum and plastic remains
into strong but  lightweight and pliable tiles.
We hired a local builder and his brother to put up the roof.
The weather cooperated, cloudy but without rain.
Nov 10 - The finished roof, nicely rounded with a small circular saw.
Another view of the completed roof.
The space between the wall and roof must now be filled in. Eventually the roof
will be supported by the wall and some of the posts will be removed.

Handing up the cobs to be added to the top of the wall.
Cob meets roof.

We created vent holes with screening. 
Dec 28 -The walls of the two bedrooms and the bathroom are almost completed.

Jan 17, 2017 - Now it's time to work on the two level floor:
living room above, entry-level kitchenette below.

Guy empties one of the unending wheelbarrows of gravel. At the back sits a
handmade water level. 

Lolita and Cindy inspect the premises while Guy starts filling the lower level.
The tamper is used to make the floor as solid as possible.

Stones, gravel and sand are delivered just outside our property since the
bridge isn't strong enough for heavy trucks.

It's a pretty stretch but long after about twenty cartfuls. 
Especially since its' uphill.

Feb 1 - The next floor layer is made of earth, sand, gravel and straw.
It's pocked so that the next layer will adhere. 

We decided to make a ramp between levels since we have a wheelchair-bound
friend. And, who knows, we might need it ourselves in the future.

Feb 7 - Now we're placing the used windows we bought back in October. 
The three large windows have to be propped and tied in place until
the walls go up around them.


We get an idea of what the windows will look like from the outside. The space looks smaller from this perspective.



Today, a week later (February 22) I took the final photos for this update. 



The cob has gone up almost two feet, holding the windows firmly in place. 



Since we've decided to wait a few weeks before building the front wall with its doorways and window, the cob wall has been tapered so that the next piece of wall supporting the main doorway will join more securely.



                     The space looks inviting in the morning sun. The tall window at right will open into an alcove.
(I just realized I should have a photo taken from the same angle as the first photo in this post. I'll take that picture and get it posted as soon as I can.) Feb 23: Here it is:

The cob house as of February 23, 2017